Contact us
MENU

61

turbines installed and connected to the grid

152m

height of wind turbines

Dec 2017

construction completed

170 000

homes powered
Wind Turbine Facts
FAQs

Construction process

Road Construction

Road Construction

To facilitate the delivery of the turbines, access roads were constructed to each turbine location. In total 33,9 kilometres of road was constructed.

 

Foundation construction

Foundation construction

Each wind turbine foundation is 19m in diametre and made of concrete and steel and placed below ground level. Each base uses over 60 truck loads of concrete.

Cabling

Cabling

The cables that bring the power from each wind turbine to the substation are buried underground.

Substation construction

Substation construction

All the cables meet at the substation where the electricity is transmitted onto transmission line.

Wind turbine delivery

Wind turbine delivery

The wind turbine towers for Khobab Wind Farm travelled along the N1 from Atlantis near Cape Town, where they were manufactured to the site.

The blades and nacelles came from overseas through a nearby port and were transported by road to the wind farm. Delivery of turbines commenced in November 2016.

 

Wind turbine parts laid down

Wind turbine parts laid down

On delivery, the turbine parts were laid down alongside the respective foundations ready for lifting by crane.

Wind turbine lifting

Wind turbine lifting

It takes two cranes working together to build each turbine.

Completion

Completion

Once the turbine was built, it was commissioned and tested and then put into operation.

Operation

Operation

Construction is now complete and the project will operate for 20 years.

61

turbines installed and connected to the grid

152m

height of wind turbines

Dec 2017

construction completed

170 000

homes powered
Wind Turbine Facts
FAQs